Sustainable, innovative, homely
We are moving into a new working environment: Where our industrial building on Neugutstrasse in Wallisellen previously stood, an innovative new building made of wood has been constructed. Experience the construction progress live in pictures and videos. Follow the construction progress live, in pictures and videos.
Since December 2023, our new address is Neugutstrasse 14a, 8304 Wallisellen
Our Baggiwood building wins the Best Architects Award 2025
Further details and key data on the building
From the ground to the erecting tree in 8 weeks (April 2023)
With Televista, the Walliseller television on the construction site (April 2023)
Carving by carving... (March 2023)
From Swiss tree to new building (February 2023)
Christmas at the construction site (December 2022)
Insulating and concreting in the basement (October 2022)
Visit to the construction site (September 2022)
Excavation (July 2022)
Raised to the ground (April / May 2022)
Built 1948 as factory of Contraves AG
1983 - 2022 Headquarters of A. Baggenstos & Co. AG
April / May 2022 demolished in one week
Fire alarm (April 20, 2022)
Dredging at Baggis (beginning of April 2022)
Starting signal for demolition (March 2022)
Aa zelle Bölle schelle, s'Baggis züglet z' Walliselle
(This is a untranslatable saying in Swiss dialect. It is derived from a counting rhyme for children and means approximately: Count down, peel onions, Baggi takes off for Wallisellen. The saying has its origin directly in Wallisellen.)
Facts & Figures
Start of construction |
March 22 |
Pollutant remediation |
March 22 |
Deconstruction / Excavation / Special civil engineering |
April 22 - June 2022 |
Relocation sewerage |
June / Juli 22 |
Shell (solid) |
August 22 |
Shell (timber construction) |
February 23 |
Building tight |
May 23 |
Interior design |
May 23 |
Installations |
August 23 |
Ready to move in |
December 23 |